Working at heights SWMS template Australia
If anyone can fall more than 2 metres — first-floor eaves, a void, a ladder that puts the working platform over that line — this is high-risk construction work. You need a SWMS before the first foot leaves the ground. A JSA for interior painting does not cover the eave.
When a working-at-heights SWMS is the right document
HRCW category: risk of a person falling more than 2 metres (model WHS regulation 291 / Schedule 3). Domestic work is not exempt. A weatherboard bungalow in Earlwood still counts.
Use this SWMS for eaves, voids, incomplete floors, and any ladder or platform where a fall would be over 2 m. Use a painting JSA only when the whole task stays on the ground floor under 2 m.
The SWMS must say how edge protection, exclusion and access will be implemented, monitored and reviewed — not just list them. Full list of categories: high-risk construction work checklist.
Filled example: first-floor eaves, Earlwood NSW
Not a roof sheet job. This example is gutter brackets and rotten eave lining on a suburban bungalow — fall from the eave to the driveway is more than 2 m. Different site and task from the warehouse roof on the roofing SWMS page.
Example layout — not a copy-paste legal document. Residual risk on a live eave often stays High. Edge protection goes in before anyone works at the soffit. Ground-floor painting under 2 m is a JSA, not this SWMS.
| Step | Hazards | Controls | 5×5 risk |
|---|---|---|---|
1. Set up the driveway exclusion zone and inspect the ground for the mobile scaffold Responsible: Supervisor |
|
| InitialL3×C4 = 12 High ResidualL2×C3 = 6 Medium |
2. Erect the mobile scaffold, fit guardrails and get a tag on before anyone works the soffit Responsible: Leading hand |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
3. Strip rotten lining and unbolt gutter brackets from the scaffold Responsible: Carpenter |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
4. Fit new lining and brackets, then dismantle the scaffold Responsible: Carpenter |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
SWMS vs JSA on the same house
Interior walls from a platform under 2 m: painting JSA. This eave: SWMS. Don’t merge them. More on SWMS vs JSA.
Frequently asked questions
Do I need a working at heights SWMS template in Australia?
Yes, if there is a risk of a person falling more than 2 metres. That is high-risk construction work under model WHS regulation 291 and Schedule 3. The SWMS has to name that category, the PCBU, the controls, and how they will be kept in place — not just say “use a ladder”.
Is a working at heights SWMS free to download?
The trial lets you generate and download a watermark-free SWMS PDF with no credit card. This page is an example layout, not a Word file you print and sign. Make the live document match the actual eave, scaffold and crew.
Is a JSA enough for first-floor eaves?
No. Ground-floor work from a platform under 2 m can be a JSA. The moment the fall is greater than 2 m — first-floor eaves, a stair void, a roof — you need a SWMS. A JSA is not a legal substitute on HRCW.
Does this SWMS work in NSW, VIC, QLD and WA?
The generator cites the WHS Act and Regulation in NSW, QLD and WA (and the other model-WHS jurisdictions). Victoria uses the Occupational Health and Safety Act 2004 and Occupational Health and Safety Regulations 2017 — pick VIC and the citations follow. The 2 m fall trigger is treated the same way on site.
What residual risk should a heights SWMS show?
Consequence of a fall from a first floor often stays 5. Residual scores of High after edge protection are normal. A heights SWMS that rates the eave as Low after “take care” is not describing the job.
Write a working-at-heights SWMS for this job
Describe the access, the fall distance and the state. Free trial, no credit card.
Start free trial →