• SWMS template · trench or shaft > 1.5 m
Excavation SWMS template Australia
A trench or shaft deeper than 1.5 metres is high-risk construction work. Ground collapse and buried services kill people on suburban blocks, not just civil jobs. If the hole stays under 1.5 m and no other HRCW applies, you may be on a JSA — this page is for when it doesn’t.
Trench deeper than 1.5 m is HRCW
HRCW: trench or shaft with excavated depth greater than 1.5 m. Collapse, engulfment, incoming services, and sometimes a confined-space overlay if the atmosphere turns. If it becomes a pit you enter with a restricted opening, also see confined space.
Filled example: sewer connection trench, Springfield Lakes QLD
New dwelling. Excavator cuts a connection trench to the council sewer — deeper than 1.5 m at the tie-in. Sandy ground, a water main marked on the BYDA plan, and a person in the hole to make the joint.
Example layout. A person in a trench deeper than 1.5 m needs shoring or a batter that actually works in that ground — not a hope. Unexpected ACM in old pipe: asbestos SWMS.
| Step | Hazards | Controls | 5×5 risk |
|---|---|---|---|
1. BYDA, locate services, and set the exclusion around the excavator Responsible: Supervisor |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
2. Excavate, batter or shore once the depth hits 1.5 m Responsible: Plant operator / leading hand |
|
| InitialL4×C5 = 20 Critical ResidualL2×C5 = 10 High |
3. Worker in the trench to lay pipe and make the sewer joint Responsible: Drainer |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
4. Backfill, compact, remove shoring Responsible: Leading hand |
|
| InitialL3×C5 = 15 High ResidualL2×C5 = 10 High |
Frequently asked questions
When do I need an excavation SWMS template?
When the work is in a trench or shaft with an excavated depth greater than 1.5 metres. That is HRCW. Shoring, battering, services and a rescue plan are part of the SWMS, not a toolbox chat.
Is the excavation SWMS free?
Trial generate and PDF, no card. This Springfield Lakes sewer trench is an example layout — sand in QLD is not clay in VIC.
SWMS or JSA for a shallow service trench?
Under 1.5 m, no collapse risk of that kind, no other HRCW: a JSA may be enough. The moment you go deeper, or you put a person in the hole, use this SWMS. Don’t “average” the depth on paper.
Valid in NSW, VIC, QLD and WA?
Yes — WHS Act/Regulation, or Victoria’s OHS Act 2004 and OHS Regulations 2017. Dial Before You Dig / Before You Dig Australia still applies everywhere.
Generate an excavation SWMS for this trench
Depth, shoring, services, state. Free trial, no credit card.